Iron Ore Holdings Ltd – Case Study of the Environmental Approval Challenges for an Emerging Junior

机译:铁矿石控股有限公司–新兴青少年环境审批挑战的案例研究

获取原文
获取原文并翻译 | 示例

摘要

Iron Ore Holdings Ltd (IOH) is an emerging junior iron ore company that is actively developingrnprojects in the Central and Western Pilbara region of Western Australia. IOH commissioned URSrnAustralia Pty Ltd (URS) in mid-2008 to prepare environmental assessment documents for thernPhil's Creek Project, which was rapidly moving into the development phase. This project comprisedrna small open cut iron ore mine that was expected to deliver approximately seven million tonnesrnover a fi ve year mine life.rnIOH faced several challenges in the environmental assessment process for the Phil's Creek Project.rnAlthough the Phil's Creek Project attained approval but has now been placed on hold, it is a usefulrncase study to discuss these challenges and how IOH addressed them. Several important lessonsrnwere learned through this process that can assist other proponents in addressing environmentalrnchallenges in a constructive and proactive manner.rnOne major challenge faced by IOH related to the endangered northern quoll (Dasyurusrnhallucatus). Another challenge was the unusually high species richness of troglofauna recordedrnwithin the project area, with several species initially known only from within the proposed pitrnfootprint.rnMeeting and overcoming these challenges has provided IOH with an increased understanding ofrnthe level of input required for consultation with government departments regarding environmentalrnassessments, and this should stand the company in good stead for developing future tenements.rnChallenges in regards to the environmental assessment process may be faced during futurerndevelopments, but IOH's experiences to date and the lessons learned from the Phil's Creek Project,rnwill help pave the way for successfully overcoming them.
机译:Iron Ore Holdings Ltd(IOH)是一家新兴的初级铁矿石公司,正在积极开发西澳大利亚州中部和西部Pilbara地区的项目。 IOH于2008年中期委托URSrnAustralia Pty Ltd(URS)为迅速进入开发阶段的rnPhil's Creek项目准备环境评估文件。该项目包括一个小型露天铁矿石矿,预计将在整个五年的矿山使用寿命中交付约700万吨的矿石。IOH在Phil's Creek项目的环境评估过程中面临若干挑战.rn尽管Phil's Creek项目已获得批准,但现在由于搁置,这是一个有用的案例研究,以讨论这些挑战以及IOH如何应对这些挑战。通过这一过程,我们吸取了一些重要的经验教训,这些经验教训可以帮助其他支持者以建设性和积极的态度来应对环境挑战。国际O​​HO面临的一项主要挑战是濒临灭绝的北方(Dasyurusrnhallucatus)。另一个挑战是在项目区域内记录的芦苇动物的物种丰富度异常高,最初仅在拟议的足迹范围内才认识到几种物种。遇到并克服这些挑战使IOH对与政府部门进行磋商所需的投入水平有了更深入的了解环境评估,这将为公司发展未来的物业单位提供良好的支持。rn在未来的发展过程中可能会面临有关环境评估过程的挑战,但是IOH迄今为止的经验以及从Phil's Creek项目中汲取的经验教训将为铺平道路。成功克服它们。

著录项

  • 来源
    《Iron ore 2011》|2011年|p.43-48|共6页
  • 会议地点 Perth(AU)
  • 作者

    H Fletcher; J Moro;

  • 作者单位

    URS Australia Pty Ltd, Level 4, 226 Adelaide Terrace, Perth WA 6000. Email: hannah_fl etcher@urscorp.com;

    URS Australia Pty Ltd, Level 4, 226 Adelaide Terrace, Perth WA 6000. Email: jenny_moro@urscorp.com;

  • 会议组织
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类 铁矿石;
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号